August 2014 work party report

The August work party was a three day effort that, despite some very heavy rain showers, managed to make considerable progress on decommissioning the Redwith site and preparing the new site. Work started on Friday […]

July 2014 work party report

This month saw the first two day work party on the new length of canal. The work involved a continuation of preparatory work around Pryces Bridge, and a major effort on the Redwith compound to […]

June 2014 work party report

This was quite a weekend! June 2014 will go down in the record books as the month when the Redwith to Pryces section saw boats for the first time since 1935, and work on the […]