April 2025 work party report

April 4-6 In glorious weather that lasted all weekend we welcomed guests from Shropshire Council, Canal & River Trust and many others on Friday to celebrate the topping out of the re-watered sections. The works […]

March 2025 work party report

March 7-9 Following the harsh weather conditions endured over the last three work parties, this time we were blessed by warm, spring sunshine. Ideal for lining and blocking. Friday started with a visit from Jason […]

February 2025 work party report

February 7-9 The winter programme of environmental works is complete. During this time, 170 metres of channel has been cleared of scrub, 720 hedging whips have been planted, a further 74 metres of hedge has […]

January 2025 work party report

January 10-12 With temperatures down to -7oC overnight, ‘bonfire management’ was a popular activity. Severe cold weather in the days before and during this work party resulted in frozen ground, frozen channel and plenty of […]

December 2024 work party report

December 6-8 Defined by Darragh. Whilst spared the very worst of Storm Darragh endured by other parts of the country, we still suffered a washout on Saturday. One hour of hedge planting was sufficient to […]

November 2024 work party report

November 1-3 This work party saw the completion of all channel and towpath deliverables for the original scope of the Rural Prosperity Fund grant – five months ahead of schedule! Given the torrential rain and […]

October 2024 work party report

October 4-6 In what promised to be a full-on work party with a tense finish, we crossed the line with hours to spare. The challenge? To complete all the channel works and construct a temporary […]