April 2017 work party report

The April event attracted near record numbers of volunteers (16,23 and 18 for the respective days) who got through prodigious amounts of work spread on three separate sites. The main tasks over the three days […]

March 2017 work party report

This may have been the first restoration work party of the year but it didn’t feel like it. The main reason for this, of course, was that the Society’s efforts over the winter had been […]

Winter 2016/2017 work parties report

This winter, rather than hedge-laying, we are clearing and coppicing the hedges between bridges and 84 and 85, in preparation for further channel restoration. The ‘hedge’ here has not been laid for so long that […]

November 2016 work party report

This may have been the last scheduled restoration work party this year but it distinctly lacked any ‘end of term’ feeling. One of the reasons for this was undoubtedly the boost to morale caused by […]

October 2016 work party report

This was one of the most productive work parties to date on the current Phase 1A section. The three day effort saw the newt ponds, the stonework on the mooring wall, and the shaping of […]

September 2016 work party report

Society volunteers were in action at three separate locations over the four days of the September work party. The main construction work was on the newt ponds at Redwith, and on the mooring wall back […]

August 2016 work party report

The well attended three day August work party was a highly productive effort which literally broke new ground. Substantial progress was made on the mooring, and the culvert was finally finished. However perhaps the most […]

July 2016 work party report

This was a remarkable work party during which substantial progress was made on the two ‘big ticket’ items on the current section. The plan was to finish the blocklaying on the mooring and to complete […]

June 2016 work party report

Since these work party reports often bemoan the rain/cold winds/hail/snow/frost which adversely affect progress, it might seem churlish to complain that the weather during the June event was a bit too hot for physical work. […]

May 2016 work party report

The May work party is usually close to the top of any list of the most productive events during the Society’s restoration season. This year’s event was no exception. One reason for this is that […]