April 2023 Crickheath South work party report

April 14-16 The April work party focussed on Phase 1A (Crickheath Wharf area) and was characterised by new tasks, high volunteer numbers and great progress. Work on repairs to the former tramway wharf south of […]

March 2023 Crickheath South work party report

March 3-5 This work party is best characterised by the 3 P’s: Plant, Progress and Pace. An outstanding achievement thanks to the volunteers’ efforts and some kind weather. Traditionally, March is the first month when […]

February 2023 Crickheath South work party report

February 3-5 Another spectacularly productive work party. We have now settled in to our new compound at Crickheath, a wide variety of preparatory tasks were completed and we are now ready for plant operations to […]

December 2022 work party report

December 2-4 Although this was officially the last work party on the Pryces to Crickheath section, there was little time for retrospection. As well as work decommissioning both LAF and Crickheath compounds, work continued in setting […]

November 2022 work party report

November 4-6 and 18-20 Although the channel construction is now finished, there was still plenty to occupy the Society’s volunteers during the month’s two work parties. As well as putting the final touches to the new […]

October 2022 work party report

October 7-9 and 21-23 Six days of concerted effort resulted in the removal of the clay dam at Crickheath; the lining and blocking of the remaining section of channel; infill of the remaining land drain […]

Drone footage of the Montgomery Canal restoration site

Work party volunteer Howard Dalton kindly took some drone footage of the section of the Montgomery Canal that is currently being restored. The photos and video illustrate the fantastic progress that has been over the […]