October 2025 work party report

October 2-5 Although uncomfortably wet and windy at times, we were spared the worst of Storm Amy and much was achieved. As last month, the main work areas were Phase 2 (joining on from the […]

September 2025 work party report

September 4-7 New compound, new era A superbly productive work party, aided by a handful of volunteers attending on Thursday for preparations in the new compound – but all of that later. First, a location […]

August 2025 work party report

August 1-4 We’ve moved! Over a work party extended to four days, the two main events were starting work in Phase 2 and relocating the compound. Phase 2 of the Crickheath South project is the […]

July 2025 work party report

July 4-6 & 9-10 It’s gone. The gap is no more. RIP. July was marked by two extra work party days thanks to large numbers of corporate volunteers from Colas Rail during the week following […]

June 2025 work party report

June 6-8 Mind the gap – it’s getting smaller. The June work party was preceded by three days pumping out the rewatered section of Phase 1B. This was necessary in order to allow removal of […]

May 2025 work party report

May 2-4 Another highly productive work party. Helped by the prolonged dry and sunny spell, profiling, lining and blocking continued to be the main event but, as usual, a variety of other tasks were undertaken. […]

April 2025 work party report

April 4-6 In glorious weather that lasted all weekend we welcomed guests from Shropshire Council, Canal & River Trust and many others on Friday to celebrate the topping out of the re-watered sections. The works […]

March 2025 work party report

March 7-9 Following the harsh weather conditions endured over the last three work parties, this time we were blessed by warm, spring sunshine. Ideal for lining and blocking. Friday started with a visit from Jason […]

February 2025 work party report

February 7-9 The winter programme of environmental works is complete. During this time, 170 metres of channel has been cleared of scrub, 720 hedging whips have been planted, a further 74 metres of hedge has […]

January 2025 work party report

January 10-12 With temperatures down to -7oC overnight, ‘bonfire management’ was a popular activity. Severe cold weather in the days before and during this work party resulted in frozen ground, frozen channel and plenty of […]