January 2026 work party report

January 9-11 “Snow stopped play” (on Friday). Although other areas fared far worse, the effects of Storm Goretti brought us different conditions each day: Friday snow; Saturday frosty but bright; Sunday cold, damp and breezy. […]

The Enhancement Group in 2025

Our enhancement group, based at Ellesmere and now in its third year, racked up over 300 hours of volunteer effort on the Llangollen Canal during 2025. A wide variety of light maintenance and improvement activities […]

December 2025 work party report

December 5-7 Muddy. The weather lately has been making up for the dry summer but we finish the year with a flourish. The main activities for the December work party were towpath construction, channel profiling […]

November 2025 work party report

November 7-9 Works to March next year are supported by a grant from the Shared Prosperity Fund which covers channel restoration, towpath restoration and the winter environmental programme. This month saw the start of towpath […]

October 2025 work party report

October 2-5 Although uncomfortably wet and windy at times, we were spared the worst of Storm Amy and much was achieved. As last month, the main work areas were Phase 2 (joining on from the […]

September 2025 work party report

September 4-7 New compound, new era A superbly productive work party, aided by a handful of volunteers attending on Thursday for preparations in the new compound – but all of that later. First, a location […]

August 2025 work party report

August 1-4 We’ve moved! Over a work party extended to four days, the two main events were starting work in Phase 2 and relocating the compound. Phase 2 of the Crickheath South project is the […]

July 2025 work party report

July 4-6 & 9-10 It’s gone. The gap is no more. RIP. July was marked by two extra work party days thanks to large numbers of corporate volunteers from Colas Rail during the week following […]

June 2025 work party report

June 6-8 Mind the gap – it’s getting smaller. The June work party was preceded by three days pumping out the rewatered section of Phase 1B. This was necessary in order to allow removal of […]

May 2025 work party report

May 2-4 Another highly productive work party. Helped by the prolonged dry and sunny spell, profiling, lining and blocking continued to be the main event but, as usual, a variety of other tasks were undertaken. […]